Escalation clause
An escalation clause is a provision that may be included in a construction contract to allow for adjustments in the contract price based on fluctuations in the cost of materials, labour, or other project-related expenses. This clause is designed to manage the risk associated with price volatility over the duration of a project. Escalation clauses are commonly used in long-term projects or those involving significant amounts of raw materials that are subject to market fluctuations. They are particularly relevant in times of economic instability or high inflation.
The primary purpose is to protect both the contractor and the client from the financial impact of significant cost changes that could not have been anticipated at the time of contract signing. It ensures that contractors are not unfairly penalised by unforeseen price increases and that clients are not overcharged.
The clause typically specifies the conditions under which price adjustments can be made. Common triggers include:
- Increases in the cost of materials.
- Changes in labour costs due to new wage agreements or labour shortages.
- Variations in fuel or transportation costs.
Escalation clauses may be calculated based on:
- A predetermined percentage increase at specified intervals.
- Adjustments based on actual cost changes, with detailed documentation.
- Adjustments based on specific cost indexes relevant to the construction industry.
This provides a transparent and objective method for determining the price changes. The contract will also outline how often price adjustments can be made. This might be on a monthly, quarterly, or milestone basis, depending on the length and nature of the project.
To prevent excessive adjustments, escalation clauses may include caps or limits on the amount by which the contract price can be increased. This protects clients from unlimited cost escalation and provides a clear framework for managing potential increases.
The contractor is usually required to provide detailed documentation supporting any claimed increases, and there may be a requirement for prior notification before adjustments are applied. This ensures transparency and allows for verification by the client or their representatives.
See also: Fluctuations and Escalation.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.