Escalation clause
An escalation clause is a provision that may be included in a construction contract to allow for adjustments in the contract price based on fluctuations in the cost of materials, labour, or other project-related expenses. This clause is designed to manage the risk associated with price volatility over the duration of a project. Escalation clauses are commonly used in long-term projects or those involving significant amounts of raw materials that are subject to market fluctuations. They are particularly relevant in times of economic instability or high inflation.
The primary purpose is to protect both the contractor and the client from the financial impact of significant cost changes that could not have been anticipated at the time of contract signing. It ensures that contractors are not unfairly penalised by unforeseen price increases and that clients are not overcharged.
The clause typically specifies the conditions under which price adjustments can be made. Common triggers include:
- Increases in the cost of materials.
- Changes in labour costs due to new wage agreements or labour shortages.
- Variations in fuel or transportation costs.
Escalation clauses may be calculated based on:
- A predetermined percentage increase at specified intervals.
- Adjustments based on actual cost changes, with detailed documentation.
- Adjustments based on specific cost indexes relevant to the construction industry.
This provides a transparent and objective method for determining the price changes. The contract will also outline how often price adjustments can be made. This might be on a monthly, quarterly, or milestone basis, depending on the length and nature of the project.
To prevent excessive adjustments, escalation clauses may include caps or limits on the amount by which the contract price can be increased. This protects clients from unlimited cost escalation and provides a clear framework for managing potential increases.
The contractor is usually required to provide detailed documentation supporting any claimed increases, and there may be a requirement for prior notification before adjustments are applied. This ensures transparency and allows for verification by the client or their representatives.
See also: Fluctuations and Escalation.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.